Adjust Wrong Freight Condition
In PO
Ticket Issues:
I have created PO with Freight (FRB1) amount and then I did GR.
After that, I realised the freight amount is wrong in PO.
I am going to change the freight amount in PO, but the field is grey even
though the GR have been cancelled.
How can I change the freight amount in PO?
Solution:
Do not worry about the freight amount if you have put wrong amount
in PO and you have finished GR also.
Cancelling the GR will not help you as the Field gets greyed once GR
done. Please process the GR with the freight as it is. Then process the
MIRO-Invoice option as per GR.
Under Payment
1) Once done find out the Amount you need to further pay to the vendor.
2) Run a Sub-sequent debit in MIRO-subsequent debit option against
the same PO.
Over Paying
1) If you want to get back some money from vendor then
2) Run a subsequent-credit in MIRO-subsequent credit option against
the same PO.
Note:
But do remember that you need to run the subsequent txns only after
MIRO-Invoice run.
Get help for your SAP MM problems
SAP MM Forums - Do you
have a SAP MM Question?
SAP MM Books
SAP Material Management
Certification, Interview and Configuration Reference Books
SAP Material Management Tips
SAP MM Configuration Tips and
Materials Management Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|