What are the procurement cycle (stepwise) of imported material up
to GR(101)? What are the steps that are to be followed to reverse the GR
for imported material? What are the transaction used?
1) The procedure for imported material receipt is as follows.....
a) P.O. Generation for the
material. ME21n
b) Capture planned delivery
cost MIRO
c) Capture excise invoice
J1IEX
d) Goods Receipt
MIGO
Since we are capturing the planned delivery cost for the GR (through
MIRO) . So before returning the material we have to reverse the planned
delivery cost thru "Subsequent Credit " using MIRO. Then only return thru
MIGO will be possible.
So, the steps for cancelling the documents for imported material is:
2) a) Sub sequent credit using
MIRO
b) Return GR (delivery)
using
MIGO
c) Cancell the excise invoice
using J1IEX
These are the steps to return the imported material & cancel the
Excise Invoice capture. *--
B.Anand daivaraja
Get help for your SAP MM problems
Do you have a SAP MM Question?
SAP MM Books
SAP Material Management
Certification, Interview Questions and Configuration Reference Books
SAP Material Management Tips
SAP MM Configuration Tips and
Materials Management Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|