Individual Collective Requirement
Indicator
What is the relevance of individual/Collective Requirement indicator
from MRP4 view of material for Finished product as well as its sub assemblies
in case of make to Stock planning strategies.
Answer:
Individual & collective indicator plays a major role in MRP.
If you set Individual indicator for both header material and dependent
material, then if sale order comes for 100 qty, then During MRP run system
will create a plan order with reference to sale order and for dependent
material, system will plan dependent material as sale order relevant. System
won't consider warehouse stock for that sale order.
If you set collective indicator for dependent material system will
consider warehouse stock for dependent material.
MRP-4 as 1 : In individual planning, this indicator is used
to display the dependent requirements of a component separately.
MRP-4 as 2 : In collective requirements, this indicator is used
to display the dependent requirements of a component grouped together.
This Indicator is useful to control the planning of dependent requirements
if the main product is being planned with strategy 20 i.e.; MTO Process.
MARC-SBDKZ indicator controls whether individual or collective
customer requirements planning is allowed for dependent requirements means
low level in BOM.
If you define individual requirements for explosion, dependent requirements
for a component are shown individually on the superior low-level code.
If you define collective requirements for explosion, required quantities
for the material are summarized independently of the sales order.
In the MTO scenario, if you want to check the unrestricted raw material
stock when you run the MRP for sales order. Please check by selecting
individual/collective requirement as 2.
Please note:
- If you select individual requirement then system will not consider
available stock and generate Proposals for every single requirements.
Also you will find PR and Plan order with account assignment of Sales order
(in case of MD50).
- If you select collective requirement then system will not generate
planning proposals through MD50. In that case you have to
go for individual MRP (MD02 / MD03 / MD41 / MD42).
For FG stock you can assign to sales order through MB1B by 412
E movement type.
Get help for your SAP PP Problems
SAP PP Forum - Do you have
a SAP PP Question?
SAP Production Planning Books
SAP PP Certification,
Interview Questions and Configuration Books
SAP PP Tips
SAP PP Tips and Production Planning/Control
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|