MRP Types Procedure Description

MRP Type

You use the MRP type to assign the procedure to be used to plan a material and to control which MRP parameters can be maintained for the material in the material master record. You enter the MRP type in the material master record.

The following parameters of the MRP type are relevant for MRP:

MRP procedure
MRP procedure  Short Description
B Reorder point planning
D Material requirements planning
N No MRP
S Forecast-based planning
M Master production scheduling
Time-phased materials planning
W Replenishment (IS Retail)
Without MRP, with BOM explosion
 
The MRP procedure defines which of the following MRP types is to be used:

  • MRP
  • Consumption-based planning (reorder point)
  • MPS
Indicator Firming type

The firming type determines how order proposals are firmed and scheduled if you work with a planning time fence in the planning run.
 

Configure Path:

SPRO -> Production -> Material Requirements Planning - Master Data - Check MRP Types (tcode OMDQ)

Key that determines whether and how the material is planned. You have the following options:

1) Manual reorder point planning

- While you are using manual reorder planning you have to maintain a reorder point manually in MRP 1 view of the particular material.

2) Automatic reorder point planning

- While using the automatic reorder point you have to maintain the forecasting view in material master and you have to give forecasting model.  So here system will automatically consider the reorder point depending upon the forecasting technique.

3) Forecast-based planning

Steps:
a. Maintain Forecasting view in material master and enter the historical data and forecasting period within the Forecasting view.
b. Maintain MRP type VV in MRP-1 view
c. Carry out MRP in transaction MP30 for Individual material and MP38 for total Forecast at Plant level. The procurement proposals will be generated
d. No PIR , NO sales orders r considered.
e. After MRP run, planned orders are created for the forecast requirements.

4) Material requirements planning with forecasts for unplanned consumption.

Unplanned consumption is updated only for materials planned using MRP. This occurs in the following cases:

a. If goods are withdrawn from the warehouse without a reservation.
b. If goods are withdrawn on the basis of a reservation, but the quantity actually withdrawn exceeds the reservation.

5) Master production scheduling (MPS)

MPS is executed for selected material only based on business decision.

Maintain MRP TYPE as M0 to M4 based on your business requirement.

Use T-Code MD40 for foreground execution.

For background, create variant in MDBS and use this variant to create a job.

SAP PP Tips

See also
How MRP Type In MM MRP View 1 Works

Get help for your SAP PP Problems
Do you have a SAP PP Question?

SAP Books
SAP Certification, Functional, Basis Administration and ABAP Programming Reference Books

SAP PP Tips
SAP PP Tips and Production Planning/Control Discussion Forum

Main Index
SAP ERP Modules, Basis, ABAP and Other IMG Stuff

All the site contents are Copyright © www.erpgreat.com and the content authors. All rights reserved.
All product names are trademarks of their respective companies.  The site www.erpgreat.com is in no way affiliated with SAP AG. 
Every effort is made to ensure the content integrity.  Information used on this site is at your own risk.
 The content on this site may not be reproduced or redistributed without the express written permission of 
www.erpgreat.com or the content authors.