Two Types of Subcontracting
Relevant for PP
The following are the business scenario:
- For some service activities we have to send some materials or machines
etc outside to a vendor
- After some activities (value addition) there it will come back
to my shop floor or warehouse.
What will be the actual procedure to execute the operation so that
I can track the material movement which is going outside and coming back?
Go through these steps for subcontracting step by step method:
There are two types of subcontracting relevant for PP module:
1. Operation subcontracting
2. Assembly subcontracting.
Assembly subcontracting:
Total product can be given for subcontracting.
We have to give the raw materials to vendors and they would supply
the assembly.
This can be done with special procurement type 30 with procurement
type F.
In that case you need to create X (FG) and their child parts (A/B/C).
You need to do the following setting for the same-
1) FG material master Special Procurement type 30 in MRP-3.
2) During MRP run select indicator 3 for create purchase requisition.
3) Convert PR into PO and maintain item category L and explode the
BOM
4) In Sub-Con Purchase order, System will collect automatically its
child parts.
5) Transfer the material by Mvmt-type 541 referring the Purchase order
to the Vendor. This will give a Mat Doc Number.
6) You can receive the complete FG thru simple MIGO process mentioning.
Operation subcontracting:
Within in-house production if some capacity bottleneck exists in any
operations then you can assign this job to some vendors to carryout this
job in his premises and supply us the semi-finished part. This can be done
via control key example PP02 (external processing control key and activate
the subcontracting Check box in routing).
Option1:
1) In Control key PP02 enable external processing and in the routing
in the operation detail enable external processing under radio button sub
contract.
2) In Order type dependent parameter T code OPL8 enable reservation
/ PR creation - 3 (immediate reservation / PR creation) during release
/ confirmation.
3) Create Info record T code ME2O only for vendor no material combination.
(You are not going to issue material for the vendor through SAP) system
will not allow through ME2O since it is operation subcontract.
4) Run MRP it will not create PR directly since the it is enable in
OPL8 only after release.
5) Do the In-house operation then confirm the in -house operation in
CO11n. Once the previous operation is confirmed PR is generated automatically.
6) Then Convert PR to P.O. In purchase order only operation description
will appear. since no component is assigned. And the order type will be
F.
7) Then make separate DC (Gate pass). Consult your MM guy for this.
8) If any component is assigned to the operation. Do stock transfer
to Vendor storage location till such time it comes to factory again.
9) While return from vendor do MIGO against the P.O and it will come
settle in prod order.
10) Payment to the vendor is through service record entry concept.
Consult MM gut for this.
Option 2:
1) You have to create separate material master for that operation.
Treating that it will be a different material
2) Create Vendor master with Material and Vendor combination
3) Create BOM with header material and this material as item for the
header.
4) Create Routing for the header material with only one operation with
control key PP02.
5) Assign the item material to this operation.
6) Run MRP this will create PR automatically. Then convert PR to PO
7) Send material to the vendor through ME2O
8) Do the GR MIGO the item will come have header material and it will
automatically update in unrestricted stock.
9) Payment to the vendor will be with different not as service entry
concept consult MM guy for this.
Get help for your SAP PP Problems
SAP PP Forum - Do you have
a SAP PP Question?
SAP Production Planning Books
SAP
PP Certification, Interview Questions and Configuration Books
SAP PP Tips
SAP PP Tips and Production Planning/Control
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|