Options To Handle Manufacturing
Materials
Business question for clarification:
Component A (proc type E in mat master) has three components B,C,D
assigned to it in BOM. B,C,D have reference points. With CN33, I assign
these components, to an activity. So the three components could be seen
below this activity. Procurement type in all three comp is F i.e. external
procurement.
I saw this example in IDES project T-20000. I was wondering as why
should it be like that. Because, comp B,C,D will be procured externally
and get consumed directly in activity. There was no need for comp A with
proc type E.
MRP type in comp A is PD with strategy group 70. When MRP was run
at project level, nothing happened to this material, i.e. mat A. Comp B,C,D
could be procured the purchase req. because of external procurement F in
mat master.
Business Logic explanation:
Since comp A has not been assigned to any activity, no planned order
is created. if no planned order then no production order also. This means
comp B,C,D will simply be procured and consumed in activity while comp
A will be simply useless.
So the clear question is: why are components assigned to activities
at all. In my view, only header should be assigned if the need to be produced
in-house. The components will be procured/or produced through production
order.
If something needs to be procured externally then it will surely
need not have a BOM and hence can be directly linked to activities for
later consumption.
Answer:
You have a production BOM consisting of three components. So material
A will be produced by your project and this is why the procurement type
is 'E'. The components for it will be purchased externally - hence the
procurement type 'F'.
SAP has given two options to handle manufacturing materials.
1) BOM - Planned Order -- Production Order -- Final Item.
2) Assembly in Network.
The IDES T-20000 case is an example of 2nd point.
When you use case 2. It means that you are assembling in project network
instead of in Production Order.
In CN33 transaction, if you click on the 'transfer Button" (3rd
from left at the top), enter project def., header material (i.e. A) and
reference point, then header is also transferred to project structure.
Header will be transferred with negative quantity and with black flush
indicator flagged. All the child components (B,C,D) are transferred with
+ve qnty.
After you procure B,C,D issue them to the Network reservation. Now,
child components are consumed. When you confirm the activity to which A
is assigned , it will be posted to the WBS stock (if it is individual material)
else to plant stock (if it is collective material).
The conversion of B,C,D to A , is mentioned in the internal activity,
you can mention the work center, duration in which B,C,D are converted
to A.
The above process is adopted when entire procurement, assembly and
inventory is managed thru P.S.
Else you can assign header material (A) to network activity and run
MRP, which will create Planned Order for A and P.R. for B, C, D.
So, the above are the two options given by SAP.
Get help for your SAP PS problems
SAP PS Forum
- Do you have a SAP PS Question?
SAP Project System Books
SAP PS Books - Certification,
Interview Questions and Configuration
SAP Project System Tips
SAP PS Tips and Project System
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|