SAP SD · Practice Quiz

Available-to-Promise Check

Test your knowledge of SAP Available-to-Promise (ATP) checks in sales and delivery documents. Select the best answer(s) for each question below.

1

Which objects decide whether an availability check is carried out in a sales document?

  • a. User and Authorization
  • b. Operation and Material
  • c. Time and Location of Document Entry
  • d. Sales Organization and Distribution Channel
  • e. Requested Delivery Date and Requirements Date
2

On what is the availability check based?

  • a. Orders on Hand
  • b. Unrestricted Use Stock
  • c. Customer Consignment Stock
  • d. Safety Stock
  • e. Cumulative ATP Quantity
3

Which statements are correct about the availability check in a sales document?

Select 3 correct answers.

  • a. If the checked materials are available, an OK check mark is set for the sales order item.
  • b. If the sales order items cannot be confirmed as requested, SAP S/4HANA can display the "Review Availability Check Result" screen.
  • c. If the check is successful, the result is documented with a fully confirmed schedule line for the item.
  • d. The result of the availability check is documented via the status "checked and available".
  • e. The check marks in the "Schedule Lines Exists" field inform the user that items are not confirmed as requested.
4

In which documents can the availability check be executed?

Select 2 correct answers.

  • a. Billing Document
  • b. Debit Memo
  • c. Outbound Delivery
  • d. Credit Memo
  • e. Sales Document

Answer Key

Q1
b
Q2
e
Q3
b, c, e
Q4
c, e