Use the below settings in your SAP IMG PP Setting for above issue.
Make the following settings in the order type-dependent parameters (Customizing
for Shop Floor Control by choosing Master data -> Orders -> Define Order
Type-Dependent Parameters) : OPL8
1. With the Cost collector indicator, you decide whether you want to
collect the costs in a product cost collector. It specifies whether the
costs are collected on a manufacturing order, (production order, process
order), or product cost collector.
-
If this indicator is turned on, the costs are collected on a product cost
collector. In this case you use the functionality of Product Cost by Period.
preliminary costing, simultaneous costing, and final costing are performed
at the level of the product cost collector. In this case you calculate
the work in process and variances by period.
-
If this indicator is not turned on, the costs are collected directly on
the manufacturing order. In this case you use the functionality of Product
Cost by Order. Preliminary costing, simultaneous costing, and final costing
are performed at the level of the manufacturing orders. In this case you
normally calculate work in process and variances by lot.
2. The Distribution rule must support periodic settlement. : PP2
Now, the main prerequisites for Split order are follwoing :
An order split is allowed with the following system status:
-
Header status: Partially released, released, partially confirmed
-
Operation status of the split operation and all successors: Created, released,
partially confirmed
The order split is not allowed with the following status:
-
Header status: Created, delivered, finally confirmed, locked, technically
complete, closed, deletion indicator set.
-
Operation status of the split operation and all successors: Finally confirmed,
dispatched, partially dispatched, capacity split, capacity requirement
assigned, capacity requirement partially allocated.
-
Operation status of the split operation: Deleted.
Before an order split can be performed, you must first post all requested
confirmations for the parent order . The posting of requested confirmations
is carried out in general by scheduling the program CORUPROC1 as a background
job.
To ensure that settlement is performed without any additional variances,
the parent and child orders must be assigned to the same Product Cost Collector.
After an order split, the costs per piece can no longer be calculated for
each order, since operations and goods movements are usually not distributed
equally between parent and child. As a result, settlement by order is not
supported. Settlement is performed through a product cost collector.
Get help for your SAP PP Problems
SAP PP Forum - Do you have
a SAP PP Question?
SAP Production Planning Books
SAP PP Certification,
Interview Questions and Configuration Books
SAP PP Tips
SAP PP Tips and Production Planning/Control
Discussion Forum
Best regards,
SAP Basis, ABAP Programming and Other IMG Stuff
http://www.erpgreat.com
All the site contents are Copyright © www.erpgreat.com
and the content authors. All rights reserved.
All product names are trademarks of their respective
companies. The site www.erpgreat.com is in no way affiliated with
SAP AG.
Every effort is made to ensure the content integrity.
Information used on this site is at your own risk.
The content on this site may not be reproduced
or redistributed without the express written permission of
www.erpgreat.com or the content authors.
|